Change Orders for Home Builder

10 tasksProject ManagementHome Builder

The Change Orders process governs how any adjustment to scope, price, or schedule is identified, priced, documented, and implemented. It provides a clear path from initial request or field need through clarification, costing, written approval, and execution. Budgets, cost codes, schedules, and drawings are updated based on approved changes, preserving an accurate picture of the project. A disciplined change order process protects profitability, controls expectations, and keeps project records aligned with what is actually being built.

1Explain change order rules and expectations to client and team——5 steps

This task sets the ground rules for how changes will be handled on the project. It aligns the internal team and the homeowner on what counts as a change, how it gets priced, when work can proceed, and how timing may be affected. Clear expectations up front reduce conflict and “favor” requests that bypass the process.

  1. Review contract and company change order policy

    Read the contract sections that describe changes, including how they must be documented, who can approve them, and how schedule and price adjustments are treated. Review your company’s internal change order policy and templates so you understand required steps and approvals. Note any project-specific deviations you must follow.

  2. Create a simple explanation of the change process

    Draft a short, plain-language summary of the change process that covers how requests are made, how pricing is prepared, when work can start, and how approvals are given. Include typical timing (e.g., “we usually need X days to price a change”) and what happens if the client delays decisions.

  3. Review rules with the internal team

    Share the change order summary with the project manager, superintendent, client services, and any coordinators. Walk through who is allowed to promise changes, who handles pricing, and who updates budget and schedule. Clarify that no one should authorize extra work without a documented, approved change order.

  4. Explain change order expectations to the client

    During the client kickoff or an early meeting, review the change process in simple terms. Explain that changes will be priced and documented in writing before work proceeds whenever possible. Give examples (e.g., moving walls, upgrading finishes) and explain how it can affect timing and cost.

  5. Document and store the communication for reference

    Send the client a brief follow-up email summarizing the change order expectations and attach your simple explanation if you have one. Save this email and your internal summary in the project folder. Refer back to it if there are later disputes about how changes should be handled.

2Receive and log all change requests in a central register——5 steps

This task captures every change request—no matter how small—in one place. It ensures verbal comments, emails, and field-driven needs become trackable items instead of disappearing in conversations. A central register lets the team see total change volume, status, and financial impact at a glance.

  1. Define accepted channels for change requests

    Decide and communicate how change requests can be submitted (e.g., email to PM, client portal, written field request from superintendent). Make it clear that offhand comments or texts still need to be converted into a formal request before being acted on.

  2. Acknowledge incoming change requests

    When a client, internal team member, or trade raises a potential change, acknowledge receipt promptly. Confirm that you will review and log it, and that no work should proceed on the change until it has been priced and approved. This sets the tone that the process matters.

  3. Create a new entry in the change order register

    Open the central change order log and add a new line for the request. Include a provisional change order number or ID, date received, requester name, brief description, and initial status such as “Received – Clarification Needed.”

  4. Attach or link supporting information

    Attach or link any emails, sketches, photos, or notes that describe the requested change to the log entry or related project folder. This keeps all relevant information tied to the specific change from the start.

  5. Assign an owner for next-step analysis

    Assign a responsible person (usually the project manager or coordinator) to move the change forward through clarification and pricing. Record their name in the register so it is clear who is accountable for progress on this item.

3Clarify requested scope and gather necessary information——5 steps

This task turns a rough idea or incomplete request into a clear scope that can be priced and scheduled. It eliminates assumptions by defining exactly what is changing, where, and what constraints apply. Good clarification prevents later arguments about what the change “included.”

  1. Review the original request and related documents

    Read the change request and look at the affected plans, specs, and selections. Identify what is clearly stated and what is ambiguous or missing. Note any conflicts with existing design, code requirements, or site conditions.

  2. Discuss the request with the requester

    Schedule a quick call, meeting, or email exchange with the person who requested the change (client, superintendent, or trade). Ask targeted questions to understand their intent, preferences, and priorities (e.g., cost vs. aesthetics vs. schedule). Confirm what is “must-have” versus “nice-to-have.”

  3. Inspect the site or drawings for impacts

    If the change affects built or in-progress work, walk the site and see what has already been done. For design-only changes, review drawings to identify all impacted areas and systems (e.g., structure, MEP, finishes). Note any demolition or rework that will be required.

  4. Define the detailed scope and constraints

    Write a concise scope description that lists what will be added, removed, or modified, and in which rooms or areas. Note constraints such as required code clearances, existing conditions, or immovable utilities. Include whether existing work must be protected, removed, or patched.

  5. Update the change order log with clarified scope

    Enter the clarified scope summary and any key constraints into the change order register. Change the status to reflect that the item is ready for pricing and schedule impact analysis. Share the clarified scope with any internal team members who will help price the change.

4Obtain pricing and timing impacts from trades and suppliers——5 steps

This task gathers cost and schedule impacts for the clarified change. It coordinates quotes from trades and suppliers and calculates internal labor, materials, and overhead. The result is a complete picture of how the change affects margin and timeline.

  1. Break the change into pricing components

    Review the clarified scope and break it into pieces that map to specific trades, suppliers, and internal work. Identify which parts are subcontracted, which require new material purchases, and which involve rework or additional internal labor.

  2. Issue clear pricing requests to trades and suppliers

    Send written pricing requests to affected trades and suppliers, including the scope description, marked-up plans if needed, and any constraints or deadlines. Specify that pricing should include labor, materials, equipment, and any expected rework or demolition.

  3. Estimate internal labor, materials, and overhead

    For any work done by your own crews or overhead impacts (e.g., extra supervision, extended general conditions), prepare internal estimates. Use your standard labor rates, productivity assumptions, and any known unit costs. Include disposal or permit impacts if applicable.

  4. Identify schedule implications with the superintendent

    Discuss the change with the superintendent to understand how it will impact the schedule. Determine whether it can be integrated with minimal disruption or if it will extend specific phases or key milestones. Note if the change requires resequencing or additional mobilizations.

  5. Compile pricing and timing into a draft impact summary

    Combine trade and supplier quotes, internal estimates, and schedule analysis into a single summary. Include cost breakdowns, proposed markup, and a description of the schedule impact (days added, milestones affected, or no impact). Save this summary in the project folder tied to the change.

5Prepare formal change order proposal with clear scope and pricing——5 steps

This task translates the clarified scope and impact summary into a formal change order document. It puts scope, price, terms, and schedule impact in one place for the client to review and sign. A clear proposal reduces back-and-forth and protects you if questions arise later.

  1. Use the standard change order template

    Open the company’s change order template or system screen and enter the project information and change order number. Confirm that header fields such as client name, lot/address, and date are correct. This keeps all change orders consistent across projects.

  2. Write a detailed scope of work section

    Copy and refine the clarified scope into a clear, readable description of what is included in the change. Use bullet points or paragraphs to separate tasks and areas. State any explicit exclusions or assumptions that affect cost or expectations.

  3. Enter pricing breakdown and totals

    Input labor, material, subcontractor, and other costs as separate lines or groups, then apply the appropriate markup per company policy. Show the net change to the contract value as an increase or decrease. Double-check math and that totals match your pricing summary.

  4. Describe schedule and other impacts

    In the schedule impact section, summarize how the change affects key dates or durations. If there is no impact, state that clearly. Note any special conditions, such as required expedited decisions or temporary disruption to previously agreed sequencing.

  5. Attach supporting information and review internally

    Attach or link supporting documents like trade quotes, sketches, or marked-up plans. Have the project manager or designated approver review the change order for completeness, clarity, and margin. Once approved internally, mark the document as ready to present to the client.

6Present change order to client and obtain written approval or rejection——5 steps

This task handles the client-facing conversation about the change. It explains what is being changed, why it costs what it costs, and how it affects timing. The goal is to get a clear written decision—approve or decline—so the team knows how to proceed.

  1. Choose the right format for presentation

    Decide whether to present the change order via email, video call, or in-person meeting based on its complexity and the client’s preference. For larger or more sensitive changes, plan for a live discussion instead of sending it cold.

  2. Walk through scope, cost, and schedule clearly

    Review the scope section with the client in plain language, then walk through the pricing at a summary level unless they request more detail. Explain the schedule impact and any knock-on effects to milestones. Keep the conversation factual and link back to the original request where needed.

  3. Answer questions and capture any requested adjustments

    Allow the client to ask questions and, if they request adjustments, clarify whether those require re-pricing or a revised change order. Avoid making off-the-cuff discounts or changes without confirming margin and implications. Summarize any agreed modifications that will require a revised document.

  4. Send the change order for written signature

    Provide the client with the formal change order via e-signature tool or PDF for signature. Clearly state that work on the change will not proceed until the document is signed, except in rare pre-approved situations. Include instructions for how to sign and return.

  5. Log the client’s decision and update status

    Once the signed change order is received, update the change order register with the approval date, amount, and status. If the change is rejected, record the rejection and reason if provided. Save the signed document in the project folder and link it to related emails or notes.

7Update budget, job cost codes, and contract value for approved changes——5 steps

This task integrates approved change orders into the project’s financial structure. It adjusts the contract value, budget lines, and cost codes so cost tracking reflects what is actually being built. If this step is skipped, reports will be misleading and margin hard to manage.

  1. Adjust contract value and change order log

    Update the project’s contract value in the accounting or ERP system by adding or subtracting the net amount of the approved change. Ensure the change order register shows the same value and approval date. Verify that change order numbering and totals match across systems.

  2. Create or update budget and cost code lines

    Add new budget lines and cost codes for the change if needed, or adjust existing ones. Make sure each part of the change (labor, materials, subs) is mapped to the correct cost bucket. Avoid lumping everything into a miscellaneous line that will be hard to analyze later.

  3. Enter revised budget amounts

    Update the project budget so that each affected cost code reflects the new expected total after the change. Check that the sum of all budget changes aligns with the change order total. Document any special assumptions used in budgeting the change.

  4. Notify accounting and project team of updates

    Inform accounting, the project manager, and superintendent that the change has been loaded into financial and cost tracking systems. Share any new cost codes and how they relate to the field work so coding on future invoices will be accurate.

  5. Store backup and cross-check reports

    Save a copy of the budget update report or screen in the project folder along with the signed change order. Run a quick cost report to confirm that the new budget and contract value are appearing correctly. Resolve any discrepancies immediately.

8Update schedule and note any impacts from approved changes——5 steps

This task feeds schedule impacts from approved changes into the master project schedule. It ensures milestones and durations reflect extra work, resequencing, or delays caused by the change. A current schedule helps the team coordinate trades and communicate realistic dates to the client.

  1. Review schedule impact from the approved change

    Look at the schedule impact you defined in the change order proposal. Confirm with the superintendent whether this still holds or if field conditions require a different adjustment. Identify which activities and milestones are affected.

  2. Adjust schedule activities and dependencies

    In the scheduling tool, add or modify activities to represent the change work as needed. Update durations, start and finish dates, and dependencies between activities. Make sure the change work is placed in the correct phase and does not inadvertently overlap with incompatible tasks.

  3. Update key milestones and completion dates

    Check how the change influences key milestones such as inspection dates, walkthroughs, and completion or closing. If dates shift, update them in the schedule. Note whether the change consumes float or extends the critical path.

  4. Document the change order reference in the schedule

    Add a note or code on affected tasks linking them to the specific change order number. This makes it easier later to understand why certain delays occurred and to explain them to stakeholders if needed.

  5. Communicate schedule updates to stakeholders

    Share significant schedule changes with the project manager, superintendent, and client services. If major milestones or closing dates are affected, coordinate with whoever is responsible for client communication to ensure the homeowner is informed clearly and promptly.

9Release approved changes to field teams and suppliers with clear instructions——5 steps

This task translates an approved change order into practical instructions for the people doing the work and supplying materials. It makes sure trades, superintendent, and suppliers know exactly what is changing and when to implement it. Clear release prevents field crews from working off outdated information.

  1. Summarize the change in field-ready language

    Write a short summary of the change that focuses on what is different in the field: locations, dimensions, products, and sequence. Avoid financial jargon and instead use terms foremen will recognize from plans and specs.

  2. Update drawings, specs, and selections as needed

    Coordinate with design or drafting to issue updated drawings, details, or selection sheets that reflect the change. Clearly label revisions with dates and revision markers. Ensure old versions are removed or clearly marked as superseded.

  3. Issue written instructions to superintendent and trades

    Send the change summary and updated documents to the superintendent and affected trades, referencing the change order number. Specify when the change is to be implemented and whether any existing work must be removed or modified. Ask recipients to confirm they understand the change.

  4. Notify suppliers of material changes

    If the change affects materials already ordered or planned, inform suppliers of revised quantities, product selections, or delivery dates. Cancel or adjust existing POs as required and issue new ones for additional materials. Confirm updates in writing.

  5. Place copies of updated information in field references

    Ensure that printed sets of drawings, site binders, or digital field tools are updated with the new information. Remove or clearly mark old sheets as superseded to avoid confusion. Briefly review the change with field leaders at the next huddle if it is significant.

10Track change order status and profitability through project completion——5 steps

This task monitors all change orders over the life of the project. It tracks status, billings, and costs so you know whether changes are being executed, collected, and kept profitable. Ongoing tracking prevents unpleasant surprises at the end of the job.

  1. Maintain an up-to-date change order register

    Regularly review the change order log and update status for each item (e.g., pending pricing, sent to client, approved, rejected, in progress, complete, billed, paid). Ensure amounts and key dates are accurate and reflect the latest information.

  2. Monitor costs against each approved change

    Run job cost reports or review cost transactions coded to each change order’s cost codes. Compare actual costs to the budgeted amount for that change. Note any change orders where costs are trending higher than expected or margin is eroding.

  3. Review change order portfolio periodically with the PM

    On a regular cadence (e.g., monthly), review the full list of change orders with the project manager. Discuss open items that need action, changes not yet billed, and problem changes with low or negative margin. Decide on corrective steps where needed.

  4. Ensure billing and collections are current

    Coordinate with accounting to verify that all approved change orders have been invoiced according to contract terms and that payments are being received. Follow up on unpaid or disputed changes and document any compromises made.

  5. Reconcile and close out change orders at project end

    As the project nears completion, reconcile the final cost and revenue for each change order. Mark them as closed in the register once work is finished and payment is received or written off. Capture any notable lessons from problematic changes to feed into future estimating and process improvement.

You found the SOP

Now make sure it actually gets done.

10 tasks is the easy part. The hard part is that six months from now the project still has to run this way when you are not the one watching.

Book a demo
Jon Engquist
Jon Engquist

Founder of Subtrak · Twenty years in commercial roofing operations

“One session and this template becomes how your company actually does the work, with a name and a date on every step.”
Assigned to the right person
Scheduled from real milestones
Your how-to where it matters
A record that it happened

Every project runs your way. And you can see that it did.

Put a name and a date on every step, and the crew gets a reminder when their part comes up.

Book a demo