Submittals and Approvals Checklist for Home Builder

6 tasksPre-ConstructionHome Builder

This checklist is designed to guide a home builder specializing in custom homes through the submittals and approvals process during the pre-construction phase. It ensures that all necessary documentation is identified, collected, reviewed, and approved in a timely manner. This process is crucial for maintaining project timelines, ensuring compliance with design specifications, and facilitating clear communication between all stakeholders, including trade partners, architects, and engineers. By following this checklist, the home builder can ensure that all submittals are properly tracked and stored, minimizing the risk of delays or errors in the construction phase.

1Identify required submittals for the project——3 steps

The first step in the submittals process is to identify all the necessary documents and materials that need to be submitted for approval. This includes architectural drawings, material samples, and product data. Identifying these requirements early helps prevent delays and ensures compliance with project specifications.

  1. Review project specifications

    Examine the project specifications document to determine the required submittals. Pay close attention to sections detailing materials, finishes, and any special requirements. Note any specific deadlines for submissions.

  2. Consult with architects and engineers

    Schedule a meeting with the project architects and engineers to discuss the submittals list. Confirm that all necessary items have been identified and clarify any ambiguous requirements.

  3. Create a submittals list

    Compile a comprehensive list of all required submittals, including drawings, samples, and product data. Organize the list by priority and deadline to facilitate tracking and management.

2Collect documentation from trade partners——3 steps

Once the required submittals have been identified, the next step is to collect the necessary documentation from trade partners. This ensures that all materials and products meet the project specifications and are ready for review.

  1. Communicate submittal requirements to trade partners

    Send a detailed list of required submittals to each trade partner. Include deadlines and any specific instructions for submission. Use email or a project management platform to ensure clear communication.

  2. Receive and organize submittals

    As trade partners submit their documentation, organize the materials by category and priority. Use a digital filing system to keep track of received documents and ensure nothing is overlooked.

  3. Verify completeness of submissions

    Check each submission for completeness. Ensure that all required documents are included and that they meet the specified format and quality standards.

3Review materials against specifications——3 steps

Reviewing the submitted materials against the project specifications is critical to ensure compliance and quality. This step involves a detailed comparison of the submittals with the project requirements.

  1. Compare submittals to specifications

    Examine each submittal in detail, comparing it against the project specifications. Look for discrepancies in material type, dimensions, and performance criteria.

  2. Document any discrepancies

    If discrepancies are found, document them clearly. Note the specific areas where the submittal does not meet the specifications and prepare a report for further action.

  3. Communicate findings to trade partners

    Share the review findings with the relevant trade partners. Provide clear feedback on any discrepancies and request revised submissions if necessary.

4Coordinate with architects and engineers——3 steps

Coordination with architects and engineers is essential to resolve any issues identified during the review process. Their expertise ensures that all submittals align with the overall project design and objectives.

  1. Schedule a review meeting

    Organize a meeting with the architects and engineers to discuss the submittals and any discrepancies found. Use this opportunity to seek their input and resolve any outstanding issues.

  2. Discuss potential solutions

    Collaborate with the architects and engineers to develop solutions for any discrepancies. Consider alternative materials or design adjustments that could address the issues.

  3. Finalize submittal approvals

    Once solutions are agreed upon, finalize the approval of the submittals. Ensure that all parties are informed of the decisions and that any necessary changes are documented.

5Track approvals and revisions——3 steps

Tracking the status of each submittal is crucial for maintaining project timelines and ensuring that all necessary approvals are obtained. This step involves monitoring the progress of each submission and managing any required revisions.

  1. Update submittals tracking log

    Maintain a detailed log of all submittals, including their status, approval dates, and any required revisions. Use project management software to facilitate tracking and reporting.

  2. Follow up on pending approvals

    Regularly check the status of pending approvals and follow up with the relevant parties as needed. Ensure that any delays are addressed promptly to avoid project disruptions.

  3. Manage revisions and resubmissions

    If revisions are required, coordinate with trade partners to obtain updated submissions. Ensure that revised documents are reviewed and approved in a timely manner.

6Store final documents in the project record——3 steps

Storing the final, approved submittals in the project record is essential for future reference and compliance. This step ensures that all documentation is organized and accessible throughout the construction process.

  1. Organize approved submittals

    Compile all approved submittals and organize them by category and project phase. Use a digital document management system to ensure easy access and retrieval.

  2. Ensure document security and backup

    Implement security measures to protect the stored documents, such as password protection and regular backups. This prevents data loss and unauthorized access.

  3. Communicate document availability

    Inform all relevant stakeholders of the availability of the final documents. Provide instructions on how to access the project record and encourage its use for reference during construction.

You found the SOP

Now make sure it actually gets done.

6 tasks is the easy part. The hard part is that six months from now the project still has to run this way when you are not the one watching.

Book a demo
Jon Engquist
Jon Engquist

Founder of Subtrak · Twenty years in commercial roofing operations

“One session and this template becomes how your company actually does the work, with a name and a date on every step.”
Assigned to the right person
Scheduled from real milestones
Your how-to where it matters
A record that it happened

Every project runs your way. And you can see that it did.

Put a name and a date on every step, and the crew gets a reminder when their part comes up.

Book a demo