Construction Workflow
Welcome to the Construction Workflow SOP Template Library for Roof Repair (Commercial) roofing projects. Access free, expertly crafted Standard Operating Procedures to guide your construction phase. Our templates cover every step, from initial setup to final installation, ensuring efficient and high-quality workmanship. Download our templates today to streamline your construction process and achieve outstanding results.
Mobilize roofing crew and set up equipment on site
Step 1: Confirm Crew Assignments and Responsibilities
• Confirm crew assignments and responsibilities for the roofing project, ensuring that each team member understands their role and tasks for the day
• Assign team leads or supervisors to oversee specific sections or tasks
Step 2: Transport Roofing Equipment and Tools to the Site
• Transport roofing equipment and tools to the project site according to the mobilization plan, coordinating with logistics providers or in-house transport teams
• Confirm that all equipment arrives on-site in good condition and is properly secured
Step 3: Set Up and Stage Equipment in Designated Areas
• Set up and stage equipment in designated areas on-site, such as staging zones for materials, tools, and safety gear
• Ensure that equipment is organized and easily accessible for efficient workflow
Step 4: Inspect Equipment for Safety and Functionality
• Inspect all equipment for safety and functionality before starting work, checking for issues such as loose parts, worn components, or electrical hazards
• Address any maintenance needs or repairs promptly
Step 5: Verify that All Crew Members Have Required PPE and Training
• Verify that all crew members have the required personal protective equipment (PPE) and have received necessary safety training
• Conduct a quick check to confirm that everyone is wearing appropriate gear, such as hard hats, gloves, and fall protection
Step 6: Establish Site Boundaries and Restricted Areas
• Establish site boundaries and restricted areas to control access and maintain safety, using fencing, signage, and barriers as needed
• Clearly mark entry points, material storage areas, and safety zones
Step 7: Document Equipment Setup and Crew Mobilization in Project Records
• Document the equipment setup and crew mobilization process in project records, noting key details such as equipment placement and safety checks
Conduct site safety briefing with roofing crew
Step 1: Gather Roofing Crew for a Safety Briefing
• Gather all roofing crew members for a safety briefing at the start of each workday or before beginning a new phase of work
• Ensure that all crew members are present and equipped with the necessary PPE
Step 2: Review Key Safety Protocols and Hazard Identification
• Review key safety protocols relevant to the day’s tasks, such as fall protection, equipment operation, and emergency procedures
• Emphasize the importance of identifying and reporting potential hazards immediately
Step 3: Discuss Specific Risks Associated with Current Work Activities
• Discuss specific risks associated with the day’s activities, such as working at heights, handling heavy materials, or operating machinery
• Provide clear instructions on how to mitigate these risks and stay safe on-site
Step 4: Verify Crew’s Understanding of Safety Measures and PPE Requirements
• Verify that all crew members understand the safety measures and PPE requirements for the tasks at hand
• Conduct a quick inspection to confirm that everyone is wearing the appropriate PPE and has received necessary safety training
Step 5: Address Any Crew Questions or Concerns About Safety
• Invite crew members to ask questions or raise concerns about the safety protocols or current work conditions
• Provide clear answers and reinforce the importance of following safety guidelines
Step 6: Assign Safety Roles and Responsibilities to Crew Members
• Assign safety roles and responsibilities to designated crew members, such as first aid responders, safety monitors, and equipment handlers
• Confirm that each assigned person understands their role
Step 7: Document the Safety Briefing in Project Records
• Document the safety briefing in the project records, noting the date, key topics covered, and any issues raised by the crew
• Save the documentation for compliance audits and future reference
Coordinate with any subcontractors on site (if applicable)
Step 1: Identify Active Subcontractors and Their Roles on Site
• Identify all active subcontractors on the project site and their specific roles and responsibilities
• Confirm their scheduled tasks and timelines to avoid conflicts or overlaps with other activities
Step 2: Establish Clear Communication Channels with Subcontractors
• Establish clear communication channels with subcontractors, such as designated points of contact, daily check-ins, or shared communication platforms
• Confirm that all subcontractors are aware of the communication protocols
Step 3: Coordinate Daily Work Plans and Task Assignments
• Coordinate daily work plans with subcontractors to align tasks and schedules, ensuring that everyone understands their responsibilities and timing
• Review any dependencies or shared tasks to prevent delays or disruptions
Step 4: Monitor Subcontractor Activities and Progress on Site
• Monitor subcontractor activities on-site to ensure that their work aligns with the project schedule and quality standards
• Address any issues, conflicts, or deviations from the plan promptly
Step 5: Verify Subcontractor Compliance with Safety and Quality Standards
• Verify that all subcontractors are complying with the established safety protocols and quality standards for their tasks
• Conduct spot checks or inspections as needed to confirm adherence to safety guidelines
Step 6: Address Any Issues or Concerns Raised by Subcontractors
• Address any issues or concerns raised by subcontractors regarding site conditions, schedules, or resource availability
• Work collaboratively to find solutions and keep the project on track
Step 7: Document Subcontractor Coordination Activities in Project Records
• Document all coordination activities with subcontractors in the project records, including key decisions, changes to the schedule, and any issues resolved
Verify delivery and inventory of repair materials
Step 1: Confirm Scheduled Delivery Times with Suppliers
• Confirm the scheduled delivery times for repair materials with suppliers to ensure that deliveries align with the project timeline and site availability
• Communicate any changes to delivery schedules to the project team and crew
Step 2: Inspect Delivered Materials for Quantity and Quality
• Inspect delivered repair materials upon arrival to verify that the quantity matches the order and that all items meet quality standards
• Check for any damage, defects, or discrepancies in the materials
Step 3: Cross-Check Delivery with Purchase Orders and Packing Lists
• Cross-check the delivered materials with the purchase orders and packing lists to confirm that all items have been received as requested
• Note any shortages or overages and report them to the supplier immediately
Step 4: Document Material Deliveries and Inventory Status
• Document all material deliveries and their inventory status in the project records, noting the delivery date, supplier name, and any issues identified
• Update the project inventory log to reflect current stock levels
Step 5: Securely Store Materials on Site to Prevent Damage or Theft
• Securely store repair materials on-site to prevent damage or theft, using designated storage areas and security measures as needed
• Ensure that materials are organized and easily accessible for upcoming tasks
Step 6: Communicate Material Inventory Status to Project Team
• Communicate the material inventory status to the project team, highlighting any shortages, delays, or quality issues that need to be addressed
• Update the project schedule if material delivery issues impact upcoming tasks
Step 7: Follow Up with Suppliers to Resolve Any Delivery Issues
• Follow up with suppliers to resolve any delivery issues, such as missing or damaged items, and arrange for replacements or corrections as needed
Prepare roof deck for repair (e.g., clean, inspect)
Step 1: Conduct a Visual Inspection of the Roof Deck
• Conduct a visual inspection of the roof deck to identify any signs of damage, wear, or structural issues
• Pay attention to areas prone to moisture, rot, or impact damage
Step 2: Clear Debris and Remove Any Obstructions
• Clear debris and remove any obstructions from the roof deck, such as leaves, old fasteners, or broken tiles
• Use brooms, blowers, or vacuums to achieve a clean and safe working surface
Step 3: Check Deck Fasteners and Connections
• Check all deck fasteners and connections to ensure they are secure and free of rust or corrosion
• Tighten any loose fasteners and replace those that are damaged or missing
Step 4: Assess the Deck’s Structural Integrity
• Assess the deck’s structural integrity by inspecting key areas such as support beams, joints, and trusses
• Note any weak or compromised sections that may need reinforcement or replacement
Step 5: Prepare the Deck for the Installation of Underlayment
• Prepare the deck for the installation of underlayment by ensuring it is dry, smooth, and even
• Address any irregularities or protrusions that could interfere with the underlayment installation
Step 6: Document the Inspection Results and Deck Condition
• Document the inspection results and current deck condition in project records, including photos of key areas and any identified issues
• Save the documentation for reference during the repair process
Step 7: Communicate Findings to the Project Team and Assign Tasks
• Communicate the inspection findings to the project team and assign tasks for clearing debris, repairing fasteners, and reinforcing the deck as needed
Remove damaged roofing materials
Step 1: Identify and Mark Areas with Damaged Roofing Materials
• Identify and mark areas with damaged roofing materials, such as cracked shingles, corroded flashing, or compromised underlayment
• Use visible markers or tape to designate the sections that need to be removed
Step 2: Establish a Safe Work Area for Material Removal
• Establish a safe work area for material removal, setting up barriers, fall protection systems, and clear access points
• Ensure that all crew members are equipped with proper PPE, including gloves, hard hats, and eye protection
Step 3: Use Appropriate Tools and Techniques to Remove Materials
• Use appropriate tools and techniques to remove damaged roofing materials without causing further damage to the underlying deck
• Handle tools with care to avoid accidents or injuries
Step 4: Dispose of Removed Materials Properly
• Dispose of removed materials properly, following local regulations and environmental guidelines for waste disposal
• Separate recyclable items from general waste to promote sustainable practices
Step 5: Inspect the Roof Deck for Any Hidden Damage
• Inspect the roof deck for any hidden damage that may have been covered by the roofing materials, such as rot, mold, or cracks
• Address any additional issues identified during the inspection
Step 6: Document the Removal Process and Condition of Exposed Deck
• Document the material removal process and the condition of the exposed deck in project records, including notes and photos
• Save the documentation for quality assurance and client communication
Step 7: Communicate the Completion of Material Removal to Project Team
• Communicate the completion of material removal to the project team, confirming that the deck is ready for repairs or new installations
Repair or replace any damaged decking or structural elements
Step 1: Identify Damaged Decking and Structural Elements
• Identify damaged decking and structural elements, such as rotted boards, weakened trusses, or corroded fasteners, during the roof deck inspection
• Document the location and extent of each issue for reference during repairs
Step 2: Remove and Dispose of Damaged Materials
• Carefully remove any damaged decking or structural elements, following safety protocols and proper disposal guidelines
• Use appropriate tools to avoid causing additional damage to the surrounding areas
Step 3: Replace Damaged Decking with New Materials
• Replace damaged decking with new, high-quality materials that meet project specifications and local building codes
• Ensure that the replacement materials are securely fastened and properly aligned with the existing deck
Step 4: Reinforce Structural Elements as Needed
• Reinforce structural elements as needed, such as adding support beams, trusses, or brackets to improve the roof’s integrity
• Confirm that all reinforcements are installed according to engineering guidelines and project requirements
Step 5: Inspect Repaired Areas for Quality and Stability
• Inspect the repaired areas to verify that the new materials and reinforcements are securely installed and stable
• Check that the repaired decking meets the required load-bearing capacity and complies with safety standards
Step 6: Document Repairs and Save Photos in Project Records
• Document all repairs made, including detailed notes and photos of the repaired areas
• Save the documentation in the project records for future reference and inspections
Step 7: Communicate Repairs and Next Steps to the Project Team
• Communicate the completed repairs and next steps to the project team, ensuring that everyone is aware of the work done and ready for the next phase of installation
Install roofing underlayment and moisture barrier
Step 1: Prepare Roof Deck for Underlayment Installation
• Prepare the roof deck for underlayment installation by ensuring that it is clean, dry, and free of any debris or sharp objects
• Inspect the deck one last time for any remaining defects or irregularities
Step 2: Select Appropriate Underlayment and Moisture Barrier
• Select the appropriate type of underlayment and moisture barrier based on project specifications and manufacturer recommendations
• Confirm that the selected materials comply with local building codes and provide adequate protection
Step 3: Install Underlayment in Overlapping Sections
• Install the roofing underlayment in overlapping sections, starting from the lowest point of the roof and working upwards
• Secure the underlayment with appropriate fasteners, ensuring that there are no gaps or wrinkles
Step 4: Apply Moisture Barrier in Critical Areas
• Apply the moisture barrier in critical areas such as valleys, eaves, roof edges, and around roof penetrations
• Ensure that the moisture barrier is properly adhered and sealed to prevent water infiltration
Step 5: Check for Proper Alignment and Fastening
• Check that the underlayment and moisture barrier are properly aligned and fastened, paying attention to edges, overlaps, and seams
• Make any necessary adjustments to maintain full coverage and tight seals
Step 6: Conduct a Final Inspection of Installed Underlayment and Barrier
• Conduct a final inspection of the installed underlayment and moisture barrier to confirm that all areas are protected and free of defects
• Address any issues or weak points before proceeding with the next installation phase
Step 7: Document the Installation in Project Records
• Document the installation of the underlayment and moisture barrier in the project records, including inspection notes and photos for quality assurance
Install roofing materials (e.g., shingles, tiles, metal panels)
Step 1: Plan the Installation Sequence and Layout
• Plan the installation sequence and layout for the roofing materials, based on the project specifications and the roof’s design
• Ensure that the layout aligns with the client’s selections and any visual patterns or designs
Step 2: Start Installation from the Lowest Point of the Roof
• Start installing the roofing materials from the lowest point of the roof and work upwards to maintain proper water runoff and layering
• Use appropriate fasteners and techniques for the type of materials being installed (e.g., nails for shingles, clips for metal panels)
Step 3: Follow Manufacturer Guidelines for Spacing and Fastening
• Follow the manufacturer’s guidelines for spacing and fastening the roofing materials to ensure a secure and long-lasting installation
• Verify that all fasteners are properly driven and flush with the material surface
Step 4: Inspect Each Section for Proper Alignment and Coverage
• Inspect each section of installed roofing materials for proper alignment, coverage, and consistency with the planned layout
• Make adjustments as needed to achieve a professional and uniform appearance
Step 5: Install Ridge Caps, Hips, and Edges for a Finished Look
• Install ridge caps, hips, and edges to provide a finished and polished look to the roof
• Ensure that all caps and edges are securely fastened and properly sealed to prevent water infiltration
Step 6: Conduct a Final Inspection of Installed Roofing Materials
• Conduct a final inspection of the installed roofing materials to confirm that they meet project specifications and quality standards
• Check for any loose or improperly installed sections that may need to be corrected
Step 7: Document the Roofing Material Installation in Project Records
• Document the roofing material installation in the project records, including photos and inspection notes for quality assurance
Install flashing and other roof penetrations
Step 1: Review Roof Plans and Identify Flashing Locations
• Review the roof plans and identify all locations where flashing and roof penetrations are required, such as chimneys, vents, skylights, and valleys
• Confirm that all necessary flashing materials are available on-site
Step 2: Select Appropriate Flashing Materials for Each Location
• Select appropriate flashing materials for each location based on project specifications and the type of roof penetration
• Ensure that all materials meet quality standards and manufacturer recommendations
Step 3: Install Base Flashing Around Roof Penetrations
• Install base flashing around roof penetrations, securing it in place with appropriate fasteners and sealants
• Ensure that the base flashing extends adequately under the roofing material to provide a waterproof barrier
Step 4: Apply Counter-Flashing for Additional Protection
• Apply counter-flashing for additional protection at key locations such as chimneys, dormers, and sidewalls
• Verify that the counter-flashing overlaps the base flashing properly and is securely fastened
Step 5: Seal All Joints and Seams to Prevent Water Infiltration
• Seal all joints and seams between the flashing and roofing materials using high-quality sealants or adhesive membranes
• Check for gaps, overlaps, or exposed edges that could lead to leaks
Step 6: Inspect Flashing Installation for Proper Coverage and Alignment
• Inspect the flashing installation for proper coverage, alignment, and compliance with project specifications
• Make any necessary adjustments to ensure a secure and watertight seal
Step 7: Document Flashing Installation in Project Records
• Document the flashing installation in project records, including photos and inspection notes for quality assurance and future reference
Conduct weekly quality control inspections
Step 1: Prepare a Weekly Quality Control Checklist
• Prepare a weekly quality control checklist that outlines key areas to inspect, such as material installation, flashing, fasteners, and overall workmanship
• Align the checklist with project specifications and quality standards
Step 2: Schedule Weekly Quality Inspections with the Project Team
• Schedule weekly quality inspections with the project team, including key personnel such as the project manager, quality control inspector, and roofing crew lead
• Confirm the inspection date and time with all participants
Step 3: Conduct Visual Inspections of Key Roofing Components
• Conduct visual inspections of key roofing components, focusing on areas such as material alignment, flashing installation, penetration seals, and drainage systems
• Use inspection tools as needed to verify the quality of each component
Step 4: Record and Document Inspection Findings
• Record and document all inspection findings, including detailed notes and photos of any issues identified
• Highlight areas that require corrections, touch-ups, or additional attention
Step 5: Discuss Inspection Results with the Roofing Crew
• Discuss the inspection results with the roofing crew, emphasizing areas that need improvement or immediate action
• Provide clear instructions and timelines for completing corrective tasks
Step 6: Follow Up on Previously Identified Issues
• Follow up on any previously identified issues from past inspections to confirm that they have been properly addressed and resolved
• Update the project records with the status of all corrective actions
Step 7: Save Quality Control Reports in Project Records
• Save the weekly quality control reports in project records and CRM, linking them to the client’s file for easy reference during future inspections or project reviews
Perform site cleanup and waste disposal of roofing materials
Step 1: Establish a Cleanup and Waste Disposal Plan
• Establish a cleanup and waste disposal plan that outlines the process for collecting, sorting, and disposing of roofing debris and unused materials
• Identify specific areas for waste collection and recycling to maintain a clean and organized site
Step 2: Gather and Sort Roofing Debris for Disposal
• Gather and sort all roofing debris, such as removed shingles, nails, underlayment, and packaging materials
• Separate recyclable items from non-recyclable waste in designated bins or containers
Step 3: Use Proper Safety Measures During Cleanup
• Ensure that all crew members use proper safety measures during the cleanup, such as wearing gloves, protective footwear, and other PPE
• Handle sharp objects and hazardous materials carefully to avoid injuries
Step 4: Transport Roofing Waste to Disposal Areas
• Transport roofing waste to designated disposal areas or containers, following local regulations and environmental guidelines
• Arrange for the removal of full containers or dumpsters from the site as needed
Step 5: Inspect the Site for Remaining Debris and Materials
• Inspect the entire site for any remaining debris, nails, or unused materials that could pose a safety hazard or impact the project’s final presentation
• Use magnetic sweepers or other tools to collect small metal debris
Step 6: Clean and Organize All Tools and Equipment
• Clean and organize all tools and equipment used during the roofing work, ensuring they are in good working condition for future use
• Store tools and equipment in designated storage areas or return them to inventory
Step 7: Document the Site Cleanup and Disposal Process
• Document the site cleanup and disposal process in the project records, noting the disposal methods used and the final condition of the site
Conduct final inspection of the roofing work
Step 1: Schedule a Final Inspection with the Project Team
• Schedule a final inspection of the roofing work with key team members, including the project manager and quality control personnel
• Confirm the inspection date and time with all participants
Step 2: Use a Comprehensive Final Inspection Checklist
• Use a comprehensive final inspection checklist to review all aspects of the completed roofing work, such as material installation, flashing, sealing, and drainage
• Ensure that the checklist aligns with project specifications and quality standards
Step 3: Inspect Each Section of the Roof for Quality and Compliance
• Inspect each section of the roof thoroughly for quality and compliance with the project specifications, focusing on key elements such as alignment, fasteners, and seals
• Identify any defects, inconsistencies, or areas that require touch-ups
Step 4: Conduct Water and Leak Tests, If Applicable
• Conduct water and leak tests in critical areas, such as valleys, roof edges, and around penetrations, to confirm that the roof is fully watertight
• Address any leaks or weak points identified during the tests
Step 5: Review Safety Measures and Site Conditions
• Review the implementation of safety measures and current site conditions to confirm that all protocols have been followed throughout the project
• Verify that all temporary safety equipment has been properly removed or decommissioned
Step 6: Document the Final Inspection Findings and Required Corrections
• Document the findings of the final inspection, including any areas that require corrections or touch-ups
• Assign corrective actions to responsible team members and set deadlines for completion
Step 7: Communicate Inspection Results to the Project Team and Client
• Communicate the results of the final inspection to the project team and client, highlighting any final tasks that need to be addressed before completion
Notify client that roofing repair work is substantially complete
Step 1: Prepare a Substantial Completion Notification Document
• Prepare a substantial completion notification document that outlines the key milestones achieved and the current status of the roofing work
• Include a summary of any minor tasks or touch-ups that remain to be completed
Step 2: Schedule a Meeting or Call with the Client
• Schedule a meeting or call with the client to formally notify them that the roofing work is substantially complete
• Confirm the meeting or call date and time with the client
Step 3: Provide an Overview of the Completed Roofing Work
• Provide an overview of the completed roofing work during the meeting or call, highlighting key achievements, project milestones, and any remaining minor tasks
• Emphasize the quality and durability of the installed materials
Step 4: Review Any Outstanding Items or Touch-Ups
• Review any outstanding items or touch-ups that remain to be completed, and provide an estimated timeline for their completion
• Assure the client that these tasks will be addressed promptly to their satisfaction
Step 5: Discuss Next Steps for Final Sign-Off and Warranty
• Discuss the next steps for final sign-off and warranty activation, including any additional inspections or paperwork that may be required
• Confirm the client’s understanding of the warranty terms and the process for reporting any future issues
Step 6: Document the Notification in Project Records
• Document the substantial completion notification in the project records, including key points discussed during the client meeting or call
• Save any related correspondence or notes in the client’s file
Step 7: Follow Up with the Project Team to Complete Outstanding Items
• Follow up with the project team to complete any outstanding items identified during the meeting with the client
• Verify that all tasks are completed before scheduling the final walkthrough
Construction SOPs Your Employees Will Actually Use!
Subtrak’s game-changing SOP software helps contractors effortlessly document their processes and automatically delegate tasks to their entire project team, making sure everyone knows exactly what to do and when.
Schedule a demo today to see how Subtrak can save you time, money, and headaches!
Download Our Free eBook
Get Blueprint for Success, our free guide to scaling and systemizing your specialty trade construction business.