Project Schedule Creation for Concrete

The Project Schedule Creation workflow provides concrete contractors with a structured method for planning timelines. It includes sequencing excavation, forming, pouring, curing, and inspections. By standardizing scheduling, contractors reduce delays, improve communication with other trades, and increase efficiency. Clients benefit from accurate timelines and transparent updates, while teams gain accountability and organization. With this workflow in place, concrete companies can improve productivity, deliver consistent results, and build stronger reputations for reliability and professionalism in project execution.

Review concrete specs and structural plans

List formwork, pour, curing, and finish

List rebar install, pour zones, curing checks

Time each pour section and finish step

Align with finish carpentry, flooring, and GC punch

Factor in mix schedule, form rentals, and rebar

Create pour calendar with form/pour/strip

Forms must be set before pour; rebar before inspection

Assign dates to form, pour, finish, cure

Plan for form strip/cure windows

Review with concrete foreman

Share pour calendar with builder

Reorder pour sections due to weather

Lock in pour timeline and notify team

Use pour log to track zones and finish dates

Forms must be set before pour; rebar before inspection

Assign dates to form, pour, finish, cure

Plan for form strip/cure windows

Review with concrete foreman

Share pour calendar with builder

Reorder pour sections due to weather

Lock in pour timeline and notify team

Use pour log to track zones and finish dates